    Project: Pioneer 2 Green Hydrogen Production Facility

    Capability: Principal Contractor / Integrated Engineering Delivery

    Client: Protium Green Solutions Ltd

    Location: Baglan, Port Talbot, South Wales

    MII Engineering has successfully delivered a major milestone in the development of clean energy infrastructure in Wales through its role as Principal Contractor for the Pioneer 2 Green Hydrogen Production Facility at Baglan, Port Talbot.

    Delivered for Protium Green Solutions Ltd under an NEC4 ECC Option A contract, Pioneer 2 represents one of the largest containerised Proton Exchange Membrane (PEM) hydrogen production systems currently operating in the UK and forms a flagship project within the growing Celtic Freeport clean energy corridor.

    Protium, the UK’s largest dedicated green hydrogen energy company, appointed MII Engineering to manage the delivery of the facility through a series of structured work packages covering procurement, civils, mechanical and electrical installation, and integrated commissioning. The completed facility is built around a Nel MC500 2.5 MWe electrolyser and Haskel compression systems capable of producing up to 1,064kg of green hydrogen per day.

    The project was delivered through five carefully managed call-off packages, enabling the works to progress in a commercially transparent and technically controlled sequence. MII Engineering oversaw the procurement of balance-of-plant equipment and long-lead items before progressing through site enabling works, civil engineering, mechanical and electrical installation, and final commissioning and handover.

    Civil and structural works included the construction of foundations, hard standings and containment systems required to accommodate the containerised electrolyser and compression packages. MII Engineering also delivered the full mechanical installation scope, including process pipework, valves, instrumentation systems and integration between the electrolyser, hydrogen compression and dispensing systems.

    Alongside this, the company completed extensive electrical installation works, including LV distribution systems, control and monitoring infrastructure, earthing and bonding systems, and integration with the site’s incoming power supply.

    Commissioning activities included leak testing, nitrogen purging, integrated systems commissioning and Site Acceptance Testing, all delivered collaboratively between MII Engineering, Protium and the original equipment manufacturers. The project successfully achieved first gas on programme, with final operational handover following completion of testing activities.

    Given the safety-critical nature of hydrogen infrastructure, the project was delivered under rigorous health, safety and quality management procedures. Pioneer 2 was completed without lost-time injury or reportable incident, reflecting the high operational standards maintained throughout delivery.

    Importantly, Pioneer 2 was delivered in Wales using a Welsh supply chain, supporting regional engineering capability and reinforcing the role of South Wales within the UK’s developing hydrogen economy. The project also reflects the collaborative ethos behind Celtico, with MII Engineering – a founding member of the alliance – demonstrating the strength of specialist engineering expertise available across the region.

    The successful delivery of Pioneer 2 highlights MII Engineering’s capability to manage and deliver complex, multidisciplinary clean energy infrastructure projects safely, collaboratively and to programme, supporting the continued growth of hydrogen and wider energy transition developments across Wales and the UK.