  • Case study – MII Engineering’s role in a major UK power project

    Case study – MII Engineering’s role in a major UK power project

    Member: MII Engineering

    Project: Hirwaun Power Plant Electrical Erection

    Capability: Electrical Engineering & Installation

    Client: Metlen Energy and Metals (formerly Mytilineos)

    End Owner: Drax (Hirwaun Power Limited)

    Location: Hirwaun, Rhondda Cynon Taf, South Wales

    Contract Value: £5.38 million

    MII Engineering played a key role in the successful delivery of the Hirwaun Power Plant, a 299MW Open Cycle Gas Turbine (OCGT) peaking station developed to provide fast-response generation capacity to the UK electricity grid.

    Owned by Drax and delivered by international EPC contractor Metlen Energy and Metals, the facility represents an important investment in UK energy resilience, helping to balance the grid as increasing levels of renewable generation are brought online. Located in the Cynon Valley, the station is designed to provide dispatchable power during periods of peak demand, supporting the UK’s transition towards a lower-carbon energy system.

    Appointed by Metlen as Electrical Erection Subcontractor, MII Engineering was responsible for the complete electrical installation package across the facility, delivering works valued at £5.38 million.

    The scope encompassed the full electrical infrastructure required to support the operation of the power station, from high-voltage systems through to instrumentation, control and life-safety systems. MII Engineering installed and energised high-voltage cable networks connecting the generator, generator transformer and auxiliary transformers, alongside the installation and commissioning of low-voltage switchgear, transformers, distribution boards, motor control centres and associated power distribution systems.

    A significant element of the project involved the installation of the station’s Distributed Control System (DCS), the central control platform responsible for monitoring and operating all major plant systems. MII Engineering delivered the installation of control room cabinets, marshalling panels, field cabling, terminations and integration with the wider plant control architecture, ensuring seamless communication between operational systems across the facility.

    The project also included the installation of extensive cable containment infrastructure, instrumentation systems, site-wide earthing and bonding networks, lightning protection interfaces, fire detection and alarm systems, CCTV, security and access control systems, heat tracing circuits, external lighting and utility power supplies.

    Working within a safety-critical power generation environment required rigorous adherence to industry standards and project specifications. High-voltage installation and testing activities were undertaken by specialist operatives working to strict procedures, while containment systems, cable segregation and electrical installations were delivered in accordance with BS 7671 requirements. Earthing and bonding systems were installed and tested to BS 7430 standards, ensuring safe operation across the entire facility.

    MII Engineering also provided comprehensive pre-commissioning and commissioning support, including continuity testing, insulation resistance testing, loop checks, point-to-point verification and support throughout energisation and final handover. Each electrical discipline was managed through dedicated inspection and test documentation, providing full traceability from installation through to commissioning and project completion.

    Importantly, the project was delivered by a Welsh engineering team supported by a regional supply chain, demonstrating the significant capability that exists within South Wales to support nationally important energy infrastructure projects. The skills deployed on the Hirwaun project, including high-voltage installation, instrumentation, control systems and station earthing, are directly applicable to future developments across the power, hydrogen, nuclear and wider energy transition sectors.

    The successful completion of the Hirwaun Power Plant electrical erection package highlights MII Engineering’s ability to deliver large-scale, technically demanding electrical infrastructure projects safely, efficiently and to the highest quality standards. It is another example of the expertise available within the Celtico alliance and the important role Welsh engineering businesses are playing in delivering the UK’s future energy infrastructure.

  • CASE STUDY – SHOWCASING OUR MEMBER: MII ENGINEERING

    CASE STUDY – SHOWCASING OUR MEMBER: MII ENGINEERING

    Member: MII Engineering

    Project: Pioneer 2 Green Hydrogen Production Facility

    Capability: Principal Contractor / Integrated Engineering Delivery

    Client: Protium Green Solutions Ltd

    Location: Baglan, Port Talbot, South Wales

    MII Engineering has successfully delivered a major milestone in the development of clean energy infrastructure in Wales through its role as Principal Contractor for the Pioneer 2 Green Hydrogen Production Facility at Baglan, Port Talbot.

    Delivered for Protium Green Solutions Ltd under an NEC4 ECC Option A contract, Pioneer 2 represents one of the largest containerised Proton Exchange Membrane (PEM) hydrogen production systems currently operating in the UK and forms a flagship project within the growing Celtic Freeport clean energy corridor.

    Protium, the UK’s largest dedicated green hydrogen energy company, appointed MII Engineering to manage the delivery of the facility through a series of structured work packages covering procurement, civils, mechanical and electrical installation, and integrated commissioning. The completed facility is built around a Nel MC500 2.5 MWe electrolyser and Haskel compression systems capable of producing up to 1,064kg of green hydrogen per day.

    The project was delivered through five carefully managed call-off packages, enabling the works to progress in a commercially transparent and technically controlled sequence. MII Engineering oversaw the procurement of balance-of-plant equipment and long-lead items before progressing through site enabling works, civil engineering, mechanical and electrical installation, and final commissioning and handover.

    Civil and structural works included the construction of foundations, hard standings and containment systems required to accommodate the containerised electrolyser and compression packages. MII Engineering also delivered the full mechanical installation scope, including process pipework, valves, instrumentation systems and integration between the electrolyser, hydrogen compression and dispensing systems.

    Alongside this, the company completed extensive electrical installation works, including LV distribution systems, control and monitoring infrastructure, earthing and bonding systems, and integration with the site’s incoming power supply.

    Commissioning activities included leak testing, nitrogen purging, integrated systems commissioning and Site Acceptance Testing, all delivered collaboratively between MII Engineering, Protium and the original equipment manufacturers. The project successfully achieved first gas on programme, with final operational handover following completion of testing activities.

    Given the safety-critical nature of hydrogen infrastructure, the project was delivered under rigorous health, safety and quality management procedures. Pioneer 2 was completed without lost-time injury or reportable incident, reflecting the high operational standards maintained throughout delivery.

    Importantly, Pioneer 2 was delivered in Wales using a Welsh supply chain, supporting regional engineering capability and reinforcing the role of South Wales within the UK’s developing hydrogen economy. The project also reflects the collaborative ethos behind Celtico, with MII Engineering – a founding member of the alliance – demonstrating the strength of specialist engineering expertise available across the region.

    The successful delivery of Pioneer 2 highlights MII Engineering’s capability to manage and deliver complex, multidisciplinary clean energy infrastructure projects safely, collaboratively and to programme, supporting the continued growth of hydrogen and wider energy transition developments across Wales and the UK.

  • CASE STUDY – SHOWCASING OUR MEMBER: MII Engineering

    CASE STUDY – SHOWCASING OUR MEMBER: MII Engineering

    Member: MII Engineering

    Project: RWE Pathfinder Program – Synchronous Condenser, Major Power Infrastructure

    Value: £14 million

    MII Engineering delivered a major package of works as part of the RWE Pathfinder Programme, supporting the installation of a synchronous condenser within an established power station complex. The project formed a key element of wider infrastructure upgrades designed to enhance grid stability and support the transition to a lower-carbon energy system.

    Working within a live power generation environment, MII Engineering undertook the full mechanical and electrical installation associated with the synchronous condenser system, alongside a comprehensive range of balance of plant (BOP) works. This included the installation and commissioning of a 400kV Generator Step-Up Transformer (GSUT) and the integration of a GIS switchgear system, both critical components within the high-voltage infrastructure supporting the condenser.

    The project also involved extensive mechanical installation works, including the fabrication and installation of pipework systems with associated supports. Alongside this, the team delivered significant electrical scope, installing power and instrumentation cabling across the site. This included integration of Distributed Control Systems (DCS), battery systems and SCADA infrastructure, ensuring the new equipment could be fully monitored and controlled as part of the wider power station network.

    A comprehensive site-wide earthing system was also installed to ensure safe operation of the high-voltage equipment and to meet stringent industry safety standards.

    Delivery of the project required a highly coordinated, multi-disciplinary approach. MII Engineering managed the integration of mechanical, electrical, control and instrumentation, pipework and scaffolding disciplines across the construction programme. At peak activity, the project mobilised a workforce of more than 120 skilled personnel, drawn from across the UK to support the delivery schedule.

    Despite the complexities associated with installing new infrastructure within an operational power station, the project was delivered safely and successfully. Close coordination between engineering disciplines ensured a seamless transition from early installation phases through to final energisation of the system.

    The successful completion of the RWE Pathfinder synchronous condenser project highlights MII Engineering’s capability to deliver complex high-voltage infrastructure works safely, efficiently and on programme, demonstrating the strength of expertise within the Celtico alliance.